The Dam
Centerton Lake Dam, NJDEP Dam File No. 35-3, Pittsgrove Township. The documents below come from the NJDEP Bureau of Dam Safety file and the court record.
NJDEP letters and orders
| Date | Document |
|---|---|
| 2003-04-02 to 2004-06-01 | Four NJDEP Dam Safety letters and orders, 2003-2004 (Ex. GGG) |
| 2015-07-28 | NJDEP dam permit issued to the Association to "rehabilitate the Centerton Lake Dam" (Ex. N) |
| 2020-11-09 | NJDEP Dam Safety memorandum to the Green Acres Office of Natural Lands Management (Ex. Q-2) |
| 2021-05-24 | NJDEP letter: repair or officially decommission; schedule due July 31, 2021 (Ex. R) |
| 2021-08-11 | NJDEP letter: extension to December 31, 2021; "the lake must remain lowered" (Ex. S) |
| 2024-01-16 | NJDEP order: dam safety inspection report due April 15, 2024 (Ex. U) |
Engineering reports and studies
| Date | Document |
|---|---|
| 2002-12-04 | 2002 Regular Biennial Inspection Report, All Systems Engineering (as produced by NJDEP Dam Safety) |
| 2016-07-07 | Loftus Construction e-mail to NJDEP on the construction estimate (Ex. O) |
| 2023-08 | Princeton Hydro feasibility study, August 2023 (Assn. Ex. J) |
What the NJDEP letters say, and what the officers wrote
NJDEP, May 24, 2021: the dam "must be either repaired and brought into compliance with the Dam Safety Standards (N.J.A.C. 7:20), or officially decommissioned." [Ex. R]
NJDEP, January 16, 2024: "an Order to drain the impoundment and remove the dam may also be issued." [Ex. U]
Wheaton to NJDEP, January 30, 2020: "can confirm that we have no intentions or desire to repair the dam." [Ex. P]
Minutes signed by Wheaton, June 15, 2022: "The NJ DEP Dam Safety has deemed the dam structure a public hazard and is requiring its removal." [Ex. TT]
Wheaton to NJDEP, August 4, 2026: "When the dam has been removed, Green Acres will be ready to close on the property." [Ex. DD-2]
The State loan
Wheaton states that the Association obtained NJDEP Permit No. 1494 in 2015, activated a State rehabilitation loan of approximately $1.2 million, and drew approximately $68,879 for engineering and design work. [Wheaton Cert. paras. 7-8] Wheaton wrote to the members on April 6, 2023 that the loan had been paid off. [Ex. WW]